BImschG-Novelle: Windpark
03.07.2024 | KPMG Law Insights

BImSchG amendment to speed up approval procedures

On 17.05.2024, the traffic light parliamentary groups agreed on the amendment to the Federal Immission Control Act (BImSchG). The law is intended to create faster and less bureaucratic procedures and thus speed up approval processes. Wind turbines and other industrial plants (e.g. plants for recycling waste) should be able to be built more quickly in this way.

Early start should no longer depend on forecast decision

In future, plant operators should be able to start construction even faster. Construction prior to the granting of approval is not permitted in accordance with. § Section 8a BImSchG is already possible, but only if a forecast by the authority shows that a decision in favor of the applicant can be expected. According to the will of the traffic light, this requirement is now to be waived at the request of the applicant in the case of a permit for an installation on an existing site and in the case of a modification permit. However, it must be ensured that the provisional measures applied for are not expected to have any harmful effects on the environment, including nature conservation and water law issues.

New version of § 10 BImSchG (approval procedure)

The approval procedure acc. § 10 BImSchG is to be digitized. Among other things, licensing authorities will be able to require electronic applications in future. For people without Internet access, however, there should continue to be another, easily accessible access option. In such cases, documents could be submitted on a standard electronic storage medium, for example. In order to adequately protect trade and business secrets, project sponsors are to be granted a right of objection in accordance with the provisions of the Planning Security Act (PlanSiG). In contrast to the regulation in the PlanSiG, however, this should not result in the authority having to suspend the procedure until an interpretation has taken place. Rather, the new regulation stipulates that the authority must choose a different form of publication in this case. A corresponding regulation is also planned for the approval procedure for hazardous incidents in accordance with Section 23b BImSchG.

The procedure for involving the authorities is also to be further streamlined and accelerated for all installations that fall within the scope of the BImSchG. If an authority to be involved has not submitted a statement within the one-month period, it will in future be assumed that it does not wish to comment unless it has requested an extension. The option to extend the deadline should not be available for all systems. In the case of approval procedures for installations for the use of renewable energies or for the production of hydrogen from renewable energies, an extension of the comment period should be excluded. If the authority to be involved fails to issue a statement, the competent licensing authority should in future be able to either obtain an expert opinion at the expense of the authority to be involved or issue a statement itself.

In addition, based on the PlanSiG, the possibility of holding the discussion meeting in the form of an online consultation or by video or telephone conference is to be introduced.

Amendment to the 9th BImSchV (Ordinance on the Approval Procedure)

The traffic light coalition also wants to shorten the processing time of the authorities. The ordinance on the approval procedure is to be amended for this purpose. The authority should check the approval documents for completeness within one month. Secondly, it is stipulated that in cases in which the authority does not request the applicant to supplement the application, it is to be assumed that the application is complete with regard to the legal consequence of the start of the deadline. In the event that the documents are not yet complete in the opinion of the authority, the deadline shall commence upon receipt of the documents requested by the authority for the first time.

Time frame

The draft bill is expected to be discussed in committee on June 5, 2024 and passed into law the following day. 2. and 3rd reading by the Bundestag.

Conclusion and outlook

The draft law is a further opportunity to relieve the burden on industry in the construction of new plants and the expansion and conversion of existing plants, thus making an important contribution to strengthening Germany as a business location. The acceleration measures must be expanded further. Particular attention must also be paid to the forthcoming amendment to the Industrial Emissions Directive and its transposition into national law to ensure that the urgently needed reduction in acceleration and bureaucracy continues to exist so that the transformation processes towards climate neutrality can succeed.

 

 

Explore #more

21.11.2025 | In the media

KPMG Law Interview in Real Estate I Haufe: Substitute building materials: “Secondary is not second class”

The Substitute Building Materials Ordinance is intended to harmonize the circular economy in construction, but legal uncertainty and bureaucracy are holding it back. How can…

21.11.2025 | KPMG Law Insights

Residential construction turbo: more living space on existing properties

Since October 30, 2025, new regulations on the creation of living space have been in force in the German Building Code (BauGB). At the heart…

19.11.2025 | KPMG Law Insights

New Packaging Implementation Act tightens obligations for companies

With a new Packaging Implementation Act (VerpackDG), German law is to be adapted to the EU Packaging Regulation. The Federal Ministry for the Environment…

18.11.2025 | In the media

KPMG Law Statement in the FAZ on the subject of deepfakes

Fraudsters can easily falsify invoices or even act as company bosses. Companies can defend themselves against this, but there are no miracle weapons against AI…

17.11.2025 | KPMG Law Insights

Video surveillance in rental properties: What should landlords be aware of?

Video surveillance of rented properties is only possible under strict legal conditions. More and more owners want to keep an eye on and secure their…

13.11.2025 | KPMG Law Insights

Implementing AI in the legal department – these are the success factors

Artificial intelligence (AI) only benefits the legal department if it is implemented correctly. The technology promises to automate time-consuming routine work and fundamentally improve the…

13.11.2025 | KPMG Law Insights

First omnibus package to relax CSDDD, CSRD and EU taxonomy obligations

On November 13, 2025, the EU Parliament voted on its negotiating position regarding the so-called omnibus package, which provides for a relaxation of the CSRD,…

12.11.2025 | In the media

KPMG Law Statement in In-house Counsel: More stability under the umbrella of corporate governance

There is a lot of talk about “corporate governance” in the face of multiple crises and regulatory tendencies on the part of legislators. But what…

07.11.2025 | Deal Notifications

KPMG Law and KPMG advise Diehl Defence on the acquisition of the Tauber Group

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised Diehl Defence on the acquisition of the Tauber Group. KPMG Law provided legal…

07.11.2025 | KPMG Law Insights

Changes to the H-1B visa and their consequences for US hiring and secondment practices

President Trump’s administration has introduced two significant changes to the highly popular H-1B visa program for skilled workers: The previous random lottery will be replaced…

Contact

Dr. Simon Meyer

Partner

Friedenstraße 10
81671 München

Tel.: +49 89 5997606 5021
simonmeyer@kpmg-law.com

Dr. Florian Gonsior

Senior Manager

Tersteegenstraße 19-23
40474 Düsseldorf

Tel.: +49 211 4155597-217
fgonsior@kpmg-law.com

© 2024 KPMG Law Rechtsanwaltsgesellschaft mbH, associated with KPMG AG Wirtschaftsprüfungsgesellschaft, a public limited company under German law and a member of the global KPMG organisation of independent member firms affiliated with KPMG International Limited, a Private English Company Limited by Guarantee. All rights reserved. For more details on the structure of KPMG’s global organisation, please visit https://home.kpmg/governance.

 KPMG International does not provide services to clients. No member firm is authorised to bind or contract KPMG International or any other member firm to any third party, just as KPMG International is not authorised to bind or contract any other member firm.

Scroll