Faster Building Permits – Legal Options for Businesses

Planning and permitting procedures do not always have to delay construction projects. The law provides several options for expediting the process. To take advantage of them, building owners and project planners may need to take action as early as the project planning phase. Here is an overview of the various options for expediting the process available to project sponsors:

 

Determine whether a standard approval process is required at all

What is often overlooked: Not all construction projects require a permit. Project developers should therefore first check whether the planned construction project qualifies for an exemption—if necessary, by tailoring the plans accordingly. In fact, to create housing, several federal states have exempted certain projects from the requirement to obtain a building permit. However, these are primarily measures involving existing buildings. This includes certain renovation projects—in particular, the conversion of attic spaces for residential purposes—as well as changes in use intended to create housing. The relevant regulations can be found in:

  • 57 BayBO (Bavaria)
  • 62 HBauO (Hamburg)
  • Section 50(2)(2) of the LBO BW (Baden-Württemberg)
  • § 64, 64a HBO (Hesse)
  • Section 63 of the Building Code of North Rhine-Westphalia (NRW)

In some cases, project developers can avoid a lengthy permitting process this way. In particular, it is worth considering whether a project can be implemented within existing structures without requiring a permit and whether a new construction project—which would require a permit—can be avoided. However, even projects that do not require a permit must comply with public law requirements. The responsibility for the legal review simply shifts more heavily to the project developer.

 

Submit all required documents to trigger deemed approval, if applicable

If the project developer has submitted a complete application for a building permit, the building permit is considered automatically granted in some federal states if the authority has not made a decision on the application within a specified time limit. Project developers should therefore check early on whether a deemed approval provision applies to their project and then submit the application documents in a complete and verifiable manner. This is a prerequisite for deemed approval.

For example, Baden-Württemberg has introduced a presumption of approval for the simplified building permit procedure (Section 58(1a) of the LBO BW), as has North Rhine-Westphalia (Section 74(2) and (3) of the BauO NRW).

 

Consider standardization right from the project planning stage and take advantage of type approval

Project developers who are carrying out multiple comparable projects, developing standardized residential buildings, or using modular or serial construction methods should consider applying for a type approval. For structures intended to be erected in multiple locations using the same design or a specific system, issues that can be generalized need to be reviewed and approved only once. In the respective building permit process for each specific structure, only site-specific issues need to be clarified. These include, above all, the project’s admissibility under building planning law pursuant to Sections 29 et seq. of the German Building Code (BauGB), setback regulations, site-specific requirements for the property (such as access, utility connections, and building coverage), as well as local building codes.

To benefit from type approval, the construction concept, planning, and procurement should be structured in such a way that as many location-independent elements as possible are standardized. The more a project is customized after the fact, the less significant the acceleration effect may be.

Type approval is currently possible in most federal states, including Baden-Württemberg (Section 68 LBO BW), Bavaria (Art. 73a BayBO), Hamburg (Section 72a HBauO), Hesse (Section 77a HBO), North Rhine-Westphalia (Section 66 BauO NRW), Lower Saxony (Section 73a NBauO), and Schleswig-Holstein (Section 72a LBO SH).

 

In addition: An amendment to the BauGB is intended to speed up urban land-use planning

An amendment to the Building Code (Act on the Modernization of Urban Planning and Regional Development Law) is intended to simplify, digitize, and expedite urban land-use planning. In addition, housing construction in certain areas is to be declared a matter of overriding public interest. Housing construction projects, in particular, could benefit from this. The law is scheduled to take effect primarily on January 1, 2027.

1. Housing construction should be given greater weight in the assessment

In particular, the newly proposed Section 1(7a) of the draft BauGB is intended to give additional weight to residential construction in areas with a tight housing market. In development areas that are intended, at least in part, for residential use, residential development is to be considered in the overriding public interest and given priority in the balancing of interests. This significantly strengthens the position of residential construction projects.

2. New Flexibility for Residential Uses in the BauNVO

Project developers may gain additional opportunities for residential and mixed-use projects as a result of the proposed amendment to the Land Use Ordinance. For example, residential development is expected to become easier in core areas that have thus far primarily served retail, offices, and central facilities (Section 7 of the draft Land Use Ordinance). The new special zone category for experimental mixed-use areas (Section 11(2a) of the draft BauNVO) is also intended to create additional flexibility. This is contingent on the respective municipality designating the development areas accordingly. In general, when developing new projects, companies should examine whether locations and land-use concepts that were previously only feasible to a limited extent under planning law are now viable options.

3. Faster planning processes due to fewer participation steps

If a zoning plan must first be established or amended for a project, project developers will be able to obtain the necessary building permits more quickly in the future. To this end, the public participation procedures, among other things, are to be streamlined (Sections 3(3), 4(1), sentence 2, and 4a(2) and (3) of the draft BauGB).

4. Clear timeframes, but no guarantee of a quick plan

In the future, project developers should be able to plan their projects based on more specific timeframes. Urban land-use planning procedures should generally be completed within two years; there should be no more than twelve months between the end of the formal public participation process and the publication of the urban land-use plan (Section 4b(2) of the draft BauGB). However, these deadlines are for guidance only: according to the draft bill, exceeding them does not render the land-use plan invalid. Nevertheless, this is a legislative requirement that obligates municipalities to complete their urban land-use planning procedures, as far as possible, before the deadlines expire.

 

Conclusion: There are several ways to obtain a building permit more quickly

Building owners and project developers can help shorten the permitting process by incorporating legal options into their planning at an early stage. Depending on the project, they can avoid a standard permitting process, obtain a deemed approval, or use a type approval for multiple comparable projects. The available options also depend on the relevant state law.

The proposed amendment to the Building Code (BauGB) can expedite the start of construction in cases where building permits must first be obtained or amended. It is therefore in the best interest of project developers to take the legal framework into account as early as the site selection and project design phases.

 

 

See also:

What the “Construction Turbo” Means for Municipalities and Building Regulatory Authorities – KPMG-Law

Housing Construction Boost: More Living Space on Existing Properties – KPMG-Law

Mixed-Use Real Estate as an Opportunity for City Centers – KPMG-Law

Higher Fees for Planners Due to Cost Increases? What Clients Should Know – KPMG-Law

Explore #more

09.10.2026 | KPMG Law Insights

Claims Management for Cyber Incidents: How Insurers Actively Manage Claims

Cyber incidents are among the most complex claims scenarios for insurers. Ransomware attacks, in particular, can paralyze entire IT infrastructures—with enormous financial consequences. Insurers for …

08.10.2026 | In the media

KPMG Law Guest Column in AUTOHAUS: Consumer Credit Directive: Sales Under New Circumstances

Car dealerships should use the time remaining before the new Consumer Credit Directive takes effect to systematically review their financing and sales processes for regulatory…

08.10.2026 | In the media

KPMG Law Interview with HAUFE: Even If AI Makes a Mistake, the Board of Directors Is Still Liable

AI analyzes, makes recommendations, and helps make decisions. But who bears the consequences if it’s wrong? KPMG Law experts Nikolaus Vincent Manthey and Sabrina Riesenbeck…

30.09.2026 | KPMG Law Insights

Mixed-Use Real Estate as an Opportunity for Downtown Areas

Downtown areas should be vibrant, sustainable, and attractive. But the traditional business model behind them—retail—is becoming less and less viable. Rents are high, customers are…

28.09.2026 | Deal Notifications

KPMG Law and KPMG are advising Rohde & Schwarz on the acquisitions of NEOSAT and PHYTRONIC

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised the Munich-based technology group Rohde & Schwarz on its acquisitions of NEOSAT GmbH…

28.09.2026 | Deal Notifications

KPMG Law and KPMG are advising Diehl Defence on the acquisition of the Dr. Carls aerial imagery database

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised Diehl Defence on its acquisition of the aerial imagery database Dr. Carls GmbH.…

26.09.2026 | In the media

Op-Ed in *Lebensmittelzeitung*: PPWR Introduces New Requirements for the Food Industry

The EU Packaging Regulation (PPWR) has been in effect since August 12, 2026—and presents companies in the food industry with a question that requires urgent…

18.09.2026 | Press releases

KPMG Law Honored at the PMN Management Awards

KPMG Law was awarded first place in the Business Development category at this year’s PMN Management Awards. In addition, the project “The Agent-Based Law Firm”…

18.09.2026 | KPMG Law Insights

How the Data Act Affects the Drafting of Lease Agreements

The EU Data Act is also of great significance to the real estate industry, as modern commercial properties have become data spaces. Heating and air…

15.09.2026 | KPMG Law Insights

Reporting Deadlines for Cyber Incidents Under the GDPR, BSIG, and CRA—Every Hour Counts

After a cyber incident, companies have only 24 or 72 hours to file their initial report with the authorities. A single incident can trigger multiple…

Contact

Dr. Florian Gonsior

Senior Manager

Tersteegenstraße 19-23
40474 Düsseldorf

Tel.: +49 211 4155597-217
fgonsior@kpmg-law.com

Dr. Thies Wahnschaffe

Senior Associate

Prinzenstr. 23
30159 Hannover

Tel.: +49 511 7635078 242
twahnschaffe@kpmg-law.com

© 2026 KPMG Law Rechtsanwaltsgesellschaft mbH, associated with KPMG AG Wirtschaftsprüfungsgesellschaft, a public limited company under German law and a member of the global KPMG organisation of independent member firms affiliated with KPMG International Limited, a Private English Company Limited by Guarantee. All rights reserved. For more details on the structure of KPMG’s global organisation, please visit https://home.kpmg/governance.

KPMG International does not provide services to clients. No member firm is authorised to bind or contract KPMG International or any other member firm to any third party, just as KPMG International is not authorised to bind or contract any other member firm.

Scroll