Search
Contact
Energiespeicher, Symbolbild zu MisPeL
29.09.2025 | KPMG Law Insights

MiSpeL draft: New funding for energy storage systems and charging points

On September 18, 2025, the Federal Network Agency published a draft for the “Market integration of storage systems and charging points” (MiSpeL for short). For the first time, energy storage systems (battery energy storage system – “BESS”) and charging points can benefit from EEG funding even if they are not operated exclusively with electricity from renewable energy sources. This means that BESS operation can be optimized in a market-oriented manner and the existing flexibility potential can actually be exploited. The determination procedure must be completed by June 30, 2026 at the latest. From then on, the new funding options can be applied in practice.

Funding currently only for BESS that exclusively consume and feed in green electricity

To date, BESSs have only been able to benefit from the exclusive option under Section 19 (3a) of the German Renewable Energy Sources Act (EEG). This means that a BESS is only entitled to the market premium or feed-in tariff if it exclusively consumes electricity from renewable energies or mine gas for the purpose of intermediate storage within a calendar year and feeds the electricity generated in this BESS back into the grid. In order to take advantage of this funding opportunity, it is necessary to prove that no grid electricity and therefore (potentially) so-called gray electricity was fed into the BESS. This restriction ultimately hinders the integration of BESS into the electricity system.

The application of the exclusivity option also prevents levy netting, as this privilege requires the storage of grid electricity purchases. In addition, the use of charging points for intermediate storage is generally excluded under the exclusivity option.

Legislators have created the legal basis for two new funding opportunities

The legislator has created the conditions for two new funding opportunities, but these will only be applicable once the MiSpeL determination procedure that has now been initiated has been completed: The Act Amending the Energy Industry Act, known as the “Solar Peak Act”, which was passed on February 25, 2025, has introduced significant innovations to the EEG and the Energy Financing Act (EnFG). In addition to the existing exclusivity option pursuant to Section 19 (3a) EEG, the deferral option in Section 19 (3b) EEG and the flat-rate option in Section 19 (3c) EEG were added. BESS operators now have the opportunity to choose between these options. In addition, bidirectional charging points, i.e. those that can absorb and release energy, are included in the law for the first time. An amendment to Section 21 EnFG allows for the proportionate maintenance of the levy balance.

The legislator’s aim is to improve the framework conditions for active market participation using BESS and at the same time to promote the grid and system integration of electricity from renewable energies. According to the explanatory memorandum to the law, this is urgently needed to curb temporary generation surpluses. BESS should use their storage function to increase flexibility both on the demand side (electricity procurement with dynamic tariffs) and on the supply side (price-optimized direct marketing) and also benefit from arbitrage transactions in a bidirectional combination.

The Solar Peak Act has also introduced the regulation that charging points for electric cars will be treated like BESS in future. A charging point can collect electricity and could later feed it back into the grid. The green share would then be eligible for funding under the deferral or flat-rate option.

The changes will only apply once the Federal Network Agency has made its determinations

However, the funding options can only be utilized once the Federal Network Agency has defined the details for measuring and calculating the eligible electricity volumes. This determination procedure has now been set in motion by the MiSpeL draft.

The MiSpeL draft will be discussed publicly in a workshop on October 1, 2025. Comments can be submitted until October 24, 2025.

Federal Network Agency presents details on demarcation and flat-rate option

In future, BESS operators will be able to choose between two additional procedures in addition to the exclusive option in order to benefit from EEG funding. Operators of charging points for electric cars will only be eligible for the two new funding options.

The deferral option pursuant to Section 19 (3b) EEG

Under the demarcation option, in the case of BESS and charging points that accept mixed electricity, only the proportion that comes from renewable energies is subsidized. The eligible share must be precisely determined and verified. It is therefore “delimited” from non-eligible gray electricity.

The Federal Network Agency is authorized to create a basis for calculating the eligible share. According to the MiSpeL draft, the eligible electricity is to be determined by taking measurements every 15 minutes. The prerequisite is measurement and data provision in compliance with calibration law. Annex 1 of the MiSpeL draft contains specific formulas for the exact mathematical determination of the eligible share and takes into account various case scenarios for the combination of RE systems with BESS and/or charging points.

Although the accrual option requires considerable measuring and billing effort, it also ensures a high level of accuracy and legally compliant determination of the respective electricity quantities. It is therefore primarily aimed at larger systems and professional operators who want precise billing.

The flat-rate option pursuant to Section 19 (3c) EEG

Compared to the deferral option, the scope of application of the flat-rate option is more limited. It is only possible in the case of joint operation of solar installations and one or more BESS. In addition, all systems involved must be operated by the same operator, the installed capacity of the solar systems must be at least 30 kW and a maximum of 500 kWh per kW of installed capacity per calendar year may be subsidized.

Under the flat-rate option, a flat-rate share of the electricity fed into the grid from BESS can be considered eligible for support without each individual quantity of electricity having to be precisely measured and allocated. This is done on the basis of certain framework circumstances and within certain orders of magnitude. If the flat-rate value is exceeded, the excess electricity is deemed to originate from the grid and is not eligible for funding. Details are regulated in Annex 2 to the MiSpeL draft.

This option is particularly suitable for smaller BESS or charging points for which costly metering is not economically viable.

Rapid conclusion of the determination procedure is desirable

It is to be welcomed that the Federal Network Agency has now presented the draft for determining the market integration of storage facilities and charging points. The MiSpeL specifications have yet to be reviewed under state aid law, which is to take place in parallel with the specification procedure.

It will only be possible to apply the deferral and flat-rate option once the precise billing and verification regulations of the MiSpeL draft are legally binding and approved by the state aid authorities. A specific date for the entry into force of the MiSpeL provisions is not yet known.

It is to be hoped that the Federal Network Agency will not make full use of the statutory deadline of June 30, 2026, but will conclude the procedure earlier. This is desirable in view of the urgent need to make the electricity grid more flexible. Until then, BESS and charging point operators are recommended to prepare for the new regulations, particularly with regard to the application of the flat-rate option, and to set up an appropriate metering system.

 

Explore #more

13.11.2025 | KPMG Law Insights

Implementing AI in the legal department – these are the success factors

Artificial intelligence (AI) only benefits the legal department if it is implemented correctly. The technology promises to automate time-consuming routine work and fundamentally improve the…

13.11.2025 | KPMG Law Insights

First omnibus package to relax CSDDD, CSRD and EU taxonomy obligations

On November 13, 2025, the EU Parliament voted on its negotiating position regarding the so-called omnibus package, which provides for a relaxation of the CSRD,…

12.11.2025 | In the media

KPMG Law Statement in In-house Counsel: More stability under the umbrella of corporate governance

There is a lot of talk about “corporate governance” in the face of multiple crises and regulatory tendencies on the part of legislators. But what…

07.11.2025 | Deal Notifications

KPMG Law and KPMG advise Diehl Defence on the acquisition of the Tauber Group

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised Diehl Defence on the acquisition of the Tauber Group. KPMG Law provided legal…

07.11.2025 | KPMG Law Insights

Changes to the H-1B visa and their consequences for US hiring and secondment practices

President Trump’s administration has introduced two significant changes to the highly popular H-1B visa program for skilled workers: The previous random lottery will be replaced…

07.11.2025 | In the media

KPMG Law Statement on HAUFE: Confusion surrounding the EU Deforestation Regulation – and what companies should do now

Possibly, perhaps, under certain circumstances, the EU Deforestation Regulation (EUDR) will not be binding for large and medium-sized enterprises on December 30, 2025 and for…

06.11.2025 | KPMG Law Insights

External personnel: authorities tighten checks with AI support

AI is a blessing for many companies, but it can also quickly become a curse, especially when authorities use the technology to uncover legal violations…

06.11.2025 | KPMG Law Insights

Deforestation regulation – simplification instead of postponement?

In September, the EU Commission wanted to postpone the EUDR deforestation regulation. On October 21, 2025, it published a comprehensive proposal to simplify the EUDR

05.11.2025 | KPMG Law Insights

Employer of Record now not subject to authorization after all – change of heart at BA

On October 1, 2025, the Federal Employment Agency (BA) updated its technical directives and made a U-turn with regard to the so-called employer-of-record model: In…

03.11.2025 | KPMG Law Insights

CO₂ contracts for difference: Participation in the preliminary procedure is a prerequisite for funding

Companies can apply for funding in the preliminary procedure for the climate protection contracts program until 1 December 2025. The funding from the Federal Ministry…

Contact

Marc Goldberg

Partner

Tersteegenstraße 19-23
40474 Düsseldorf

Tel.: +49 211 4155597976
marcgoldberg@kpmg-law.de

© 2024 KPMG Law Rechtsanwaltsgesellschaft mbH, associated with KPMG AG Wirtschaftsprüfungsgesellschaft, a public limited company under German law and a member of the global KPMG organisation of independent member firms affiliated with KPMG International Limited, a Private English Company Limited by Guarantee. All rights reserved. For more details on the structure of KPMG’s global organisation, please visit https://home.kpmg/governance.

 KPMG International does not provide services to clients. No member firm is authorised to bind or contract KPMG International or any other member firm to any third party, just as KPMG International is not authorised to bind or contract any other member firm.

Scroll