05.10.2018 | KPMG Law Insights

Bill of quantities beats sampling!

Bill of quantities beats sampling!

Approval of a product through sampling does not supersede the specifications of the bill of quantities for the product. This also applies if the client was able to recognize the deviations from the specifications during the sampling.

Decision of the OLG Schleswig of August 18, 2017, Ref. 1 U 11/16

We report on a recently published decision that gives reason to examine the requirements for sampling in construction contracts and to regulate the legal consequences of a selection or approval decision more precisely.

Initial case

Client (hereinafter “Client“) and Contractor (hereinafter “Contractor“) concluded a VOB contract for the laying of tiles in a staircase. The Contractor used tiles without ceramic surface sealing and with a different slip resistance class for the landings as opposed to the stair treads as part of the execution of this contract. This resulted in the tiles on the landings looking stained after completion and acceptance, and increased cleaning requirements. The parties had contractually stipulated that all tiles used must match each other and have the same slip resistance class. The tiles actually used, i.e. also the tiles for the landings without surface sealing, were presented to the customer during a sampling appointment and approved by him. The Contractor demanded payment of the remaining remuneration for the work. The customer counterclaimed and demanded the payment of an advance to remedy the defect.

Decision

The Higher Regional Court of Schleswig ruled that the Contractor’s performance was defective because he had laid tiles that did not comply with the agreed quality. The tiles on the landings and the steps do not match each other because they have different slip resistance class and roughness, and therefore different susceptibility to dirt.

According to the court, the sampling meeting was solely about the selection of the color of the tiles. Therefore, in the present case, the Contractor cannot rely on the fact that the Client had selected the tiles himself within the scope of the sampling appointment. Whether the difference between the step tiles and the other tiles was recognizable during the sampling is even irrelevant in the opinion of the OLG Schleswig. A Baulaie could possibly recognize a certain optical deviation of the tiles. The decisive factor, however, was that he could not recognize the consequences in use without being informed by the expert contractor.

The Higher Regional Court of Schleswig also emphasized that the Contractor could not rely on the price specified in the invitation to tender. It would have been incumbent on him to inform the customer about the advantages and disadvantages of ceramic sealing. Only then would the AG have been able to make a sensible decision as to whether to choose the tiles actually presented or to request higher quality tiles at a higher price.

Practice Notes

The decision of the Higher Regional Court of Schleswig makes it clear that the agreed quality of work is generally not determined or changed by the specifications in a sampling appointment. If the parties nevertheless wish to achieve that a sampling to be carried out supersedes the specifications of the bill of quantities, this must be clearly taken into account when drafting the construction contract. For example, wording in the specifications such as “…according to sampling” can be selected for this purpose. Even this brief addition makes it sufficiently clear that the sampling carried out by the Contractor is intended to concretize the specifications of the bill of quantities and therefore takes precedence over them. If the bill of quantities is designed accordingly, it is sufficient at the sampling date that the CL was able to recognize all deviations from the bill of quantities. Further clarification of the Contractor is then not required (see OLG Bremen, judgment of March 16, 2012, Case No. 2 U 94/09). It therefore seems advisable for the Contractor to provide information in appropriate situations about the differences between certain products or makes, for example by providing data sheets or other manufacturer information, and to document this information.

Explore #more

09.09.2025 | Deal Notifications

KPMG Law and Tax advise Adiuva Capital GmbH with Fact Books on the sale of KONZMANN Group.

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised Adiuva Capital GmbH, a Hamburg-based private equity firm (Adiuva), in connection with the…

04.09.2025 | In the media

Guest article in Unternehmensjurist: Strategically transforming legal departments: A market overview

What are in-house teams at large companies concerned about when it comes to digital transformation? Which topics will be decisive in the coming years? The…

04.09.2025 | In the media

Guest article in the Unternehmensjurist: Successful change management in the HR department

The HR department plays a crucial role in the digital transformation. It is not only affected by change, but also shapes it. Between transformation, co-determination…

03.09.2025 | In the media

Guest article in the insurance industry: Embedded Insurance – More than just a new sales channel

The insurance industry is facing a paradigm shift. Traditional sales models are increasingly being supplemented by innovative approaches aimed at facilitating access to insurance policies…

03.09.2025 | KPMG Law Insights

Supply Chain Act: reporting obligation no longer applies, sanctions reduced

In the coalition agreement, the coalition partners agreed to abolish the Supply Chain Due Diligence Act (LkSG) as part of the implementation of the…

29.08.2025 | In the media

Statement by Ulrich Keunecke on the special infrastructure fund in Politico

KPMG Law financial expert Ulrich Keunecke explains how the infrastructure special fund can be leveraged with capital from private investors. You can find the article…

25.08.2025 | Deal Notifications

KPMG Law is advising APELOS on the refinancing and acquisition of a practice group with around 50 practice locations.

KPMG Law Rechtsanwaltsgesellschaft mbH (KPMG Law) and KPMG AG Wirtschaftsprüfungsgesellschaft (KPMG) advised APELOS Therapie GmbH, a leading therapy practice group in Germany, on the refinancing…

15.08.2025 | In the media

KPMG Law Statement in Die-Stiftung.de on the topic of foundation registers – The long road to digital order

The entry into force of the foundation law reform on July 1, 2023 marks a turning point in the German foundation system. The list of…

14.08.2025 | KPMG Law Insights

Electromobility in logistics – legal challenges

In order to reduce its CO2 emissions, the logistics industry is increasingly turning to electromobility. This is not only due to ESG regulations such as…

07.08.2025 | KPMG Law Insights

NIS2: How energy suppliers must protect themselves against cyber attacks

In July 2025, the Military Counterintelligence Service reported a significant increase in spying attempts and disruptive measures by the Russian secret service, according to media…

Contact

Dr. Rainer Algermissen

Partner
Head of Construction and Real Estate Law

Fuhlentwiete 5
20355 Hamburg

Tel.: +49 40 3609945331
ralgermissen@kpmg-law.com

© 2024 KPMG Law Rechtsanwaltsgesellschaft mbH, associated with KPMG AG Wirtschaftsprüfungsgesellschaft, a public limited company under German law and a member of the global KPMG organisation of independent member firms affiliated with KPMG International Limited, a Private English Company Limited by Guarantee. All rights reserved. For more details on the structure of KPMG’s global organisation, please visit https://home.kpmg/governance.

 KPMG International does not provide services to clients. No member firm is authorised to bind or contract KPMG International or any other member firm to any third party, just as KPMG International is not authorised to bind or contract any other member firm.

Scroll