Search
Contact
E-Auto an Ladestation
06.09.2024 | KPMG Law Insights

No grandfathering for charging stations: small network operators should act now

The charging station infrastructure sector is currently undergoing regulatory change.
Strict unbundling requirements apply to distribution system operators in particular in accordance with Section 7c EnWG, from which, however, exceptions also apply to the operation of charging points for distribution system operators that fall within the scope of the de minimis rule in Section 7 (2) EnWG.
These exemptions are limited to December 31, 2024.
The Federal Network Agency (BNetzA) has now clarified how things will continue after the deadline.

Background to the prohibition of unbundling under Section 7c EnWG

The strict regulatory requirement to separate electromobility from grid operation is based on the idea that charging points should be established as a competitive market level downstream of the grid level.
They must therefore be separated from grid operations in accordance with the principles of unbundling.
According to Section 7c para.
1 EnWG, the prohibition applies not only to (the ownership and) operation of the charging points, but also to their development and management.
The ban on “development”, for example, means that the grid operator may not be involved in preparatory work for the operation of the charging point.
The operator of a charging point is the person who exercises decisive influence on the operation of a charging point, taking into account the legal, economic and factual circumstances.

No exception for de minimis companies after the end of the transitional regulation

For a transitional period, Section 118 para.
34 EnWG provided for an exception for grid operators that fall under the regulatory de minimis rule of Section 7 para.
2 EnWG.
These grid operators were permitted to develop, manage and operate charging points.
Due to the time limit of the exception in Section 118 para.
34 EnWG, however, the question arises in practice as to what extent these network operators could claim grandfathering for the charging points already implemented, which would allow the charging points to be operated beyond 2024.
The BNetzA clarifies its understanding, particularly with regard to the question of the transitional provision, that network operators that fall under the de minimis rule will no longer be allowed to operate charging points from 2025.
An exception that goes beyond the current regulations is neither provided for in the EU legislation nor in the EnWG.

Need for action for network operators

If this strict application of the wording of the law and thus the BNetzA’s interpretation continues, the ban in Section 7c para.
1 EnWG must be implemented for the entire existing charging infrastructure of grid operators – regardless of size.
As a consequence, grid operators will be obliged to transfer their ownership of existing charging points if they do not wish to give them up.
However, charging infrastructure activities can be transferred to other companies in the vertically integrated group of companies, and operational management constellations are also conceivable.
Only private charging points intended for the network operator’s own use are permanently exempt from the operating ban.
However, the scope of application is very limited.
A number of questions arise in practice.
On the one hand, it is already questionable which charging stations are to be transferred: For example, it is questionable whether charging solutions provided by integrated suppliers for (private) customers or contracting offers for clinics etc. are also affected.
On the other hand, the actual implementation of such a transfer – depending on the transaction path chosen – also regularly involves very different preliminary questions of company law and tax law aspects, which are only mentioned here as examples:

  • Since options to implement the transfer by way of universal succession in a timely manner are now likely to be limited in terms of time/facts: What – possibly additional – action is required in the event of a transfer by way of singular succession?
  • Which corporate bodies are to be involved or which external third parties (e.g. contractual partners, subsidizing bodies, municipal supervisory authority) are to be additionally involved?
  • Are there any “hidden reserves” in the charging infrastructure – and if so, how can their tax-damaging disclosure be avoided?
  • What effects does the transfer have on real estate transfer tax and VAT?
  • How does the transfer (in the case of municipal energy suppliers) affect any existing “tax grouping”?

 

Explore #more

14.05.2025 | KPMG Law Insights

BGH on customer installations: Decision orders application in line with the directive

In a ruling dated May 13, 2025, the BGH classified the supply infrastructure in the specific case of a residential complex in Zwickau as a…

13.05.2025 | In the media

KPMG Law expert in Spiegel article on energy policy

Dirk-Henning Meier, Senior Manager in the energy law department at KPMG Law, is quoted in a recent article on energy policy in Der Spiegel.…

13.05.2025 | Career, In the media

azur Karriere Magazin – All AI or what?

Artificial intelligence has long since arrived in law firms and legal departments. But dealing with it is a skill that needs to be learned. Many…

13.05.2025 | KPMG Law Insights

Initial experience with the Single-Use Plastics Fund Act: what manufacturers should bear in mind

Beverage cups, foil and plastic cigarette filters litter streets, parks and sidewalks. The cleaning costs are borne by the local authorities. The Disposable Plastics Fund…

07.05.2025 | KPMG Law Insights

Termination of fixed-term rental agreements in the case of pre-leasing

In the case of a pre-leasing, the tenancy only begins at a later date, usually the handover date. In such cases, the contracting parties usually…

06.05.2025 | In the media

Wirtschaftswoche honors KPMG Law

KPMG Law was named “TOP Law Firm 2025” in the field of M&A by WirtschaftsWoche. Ian Maywald, Partner at KPMG Law in Munich, was…

06.05.2025 | KPMG Law Insights

Social insurance obligation for teachers – transitional rule creates clarity

Teachers and lecturers are often hired on a self-employed basis. This practice makes the German pension insurance fund sit up and take notice. It is…

02.05.2025 | In the media

KPMG Law Statement in FINANCE Magazine: How CFOs can save up to 80 percent in the legal department

The cost pressure in companies is increasing – also in legal departments. Two strategies have now become established to save 50 to 80 percent of…

30.04.2025 | In the media

KPMG Law study in the Neue Kämmerer: How does the special fund get into the municipalities?

A special fund of 500 billion euros is to finance investments in infrastructure over the next twelve years. Of this, 100 billion euros are earmarked…

29.04.2025 | KPMG Law Insights

Anti-money laundering and transparency register – what will the new government change?

According to the coalition agreement, the future government wants to “resolutely combat” money laundering and financial crime. The coalition partners have announced that legal…

Contact

Marc Goldberg

Partner

Tersteegenstraße 19-23
40474 Düsseldorf

Tel.: +49 211 4155597976
marcgoldberg@kpmg-law.de

Hendrik Burbach

Manager

Tersteegenstraße 19-23
40474 Düsseldorf

Tel.: +49 211 4155597 684
hburbach@kpmg-law.com

© 2024 KPMG Law Rechtsanwaltsgesellschaft mbH, associated with KPMG AG Wirtschaftsprüfungsgesellschaft, a public limited company under German law and a member of the global KPMG organisation of independent member firms affiliated with KPMG International Limited, a Private English Company Limited by Guarantee. All rights reserved. For more details on the structure of KPMG’s global organisation, please visit https://home.kpmg/governance.

 KPMG International does not provide services to clients. No member firm is authorised to bind or contract KPMG International or any other member firm to any third party, just as KPMG International is not authorised to bind or contract any other member firm.

Scroll